Project: Shared Driveways (Stewart Park)
Date: November 07, 2025
This Week’s Progress
General Communication:
- Work commencement notice posted on section 3.
Area 1 (units 3122, 3124, 3744 and 3740) and area 2 (units 3120, 3736, and 373730)
- Final clean-up.
- Remove barricades and allow access.
Area 3 (units 3141, 3124, 3718 and 3724)
- Removal of pavers on shared driveway.
All Phases
- Internal punch list walk and repairs.
Next Week’s Planned Activities
The following tasks are scheduled for completion during the week of November 10, 2025: General Communication:
- N/A
Area 3 (units 3141, 3124, 3718 and 3724)
- Sewer line repairs.
- Soil over-ex and haul off for driveway repairs.
- Soil compaction and testing.
- Form work for new-v-pan and curb.
All Phases
- Internal punch list walk and repairs.
Your Projects’ Team contact information is:
Juan Perez
Senior Superintendent | Reconstruction Experts Colorado
M 303-242-6761
Hugo Aguina
Field Engineer | Reconstruction Experts Colorado
M 720-948-5459