Weekly Construction Update – 10/24/25

Project: Shared Driveways (Stewart Park)

Date: October 24, 2025

This Week’s Progress

General Communication:

  • N/A

Area 5 (units 3144, 3146, 3704 and 3708) and area 4 (units 3145, 3143, 3712 and 3716)

  • Final clean-up and landscape restoration.

Area 1 (units 3122, 3124, 3744 and 3740) and area 2 (units 3120, 3736, and 373730)

  • Install barricades to restrict access.
  • Remove pavers in designated area.
  • Soil prep work.
  • Soil compaction testing.
  • Form work for v-pan and driveway curb.

Next Week’s Planned Activities

The following tasks are scheduled for completion during the week of October 27, 2025: General Communication:

  • Delay notice to be posted on section 3.

Area 1 (units 3122, 3124, 3744 and 3740) and area 2 (units 3120, 3736, and 373730)

  • Soil prep work.
  • Pour new v-pan and curb.
  • Soil compaction testing.
  • Final clean-up.
  • Remove barricades and allow access.

All Phases

  • Internal punch list walk and repairs.

Your Projects’ Team contact information is:

Juan Perez

Senior Superintendent | Reconstruction Experts Colorado

M 303-242-6761

E juan.perez@reconexp.com

Hugo Aguina

Field Engineer | Reconstruction Experts Colorado

M 720-948-5459

E hugo.aguina@reconexp.com

Leave a Reply

1764711710